In addition to the blog, the site features a discussion forum and a very detailed progress report in which progress on each aspect of the project can be reported. For example there are almost 40 separate benchmarks identified for the Sydney cable station alone, just one of 10 main components of the project, each with a number of sub-items. Announcing the blog to investors, CEO Bevan Slattery said the blog would be kept up to date daily with photos, videos, and staff and updates on the system's progress. He said that the project was "progressing ahead of schedule with survey underway and cable manufacture 3 months ahead of schedule."